Initial Precedence Network
This cascade diagram has been drawn using the preceding events from the table. The forward direction is from left to right, the arrows have been omitted as this is always the case throughout. Click here to view Event Details...
KEY
A
Event letter
2
Event duration (hours)
Non-critical path
Critical path
- - -
Logic/identity dummy
Precedence Network with Times
This is the precedence network showing the time, in hours, needed in order to complete each activity. The forward direction maintains to be from left to right. The critical path is shown in red. As you can see, it follows the path: B, D, E, F, G, J, K, L, M, O, P, Q, T, V. Click here to view Event Details...
This is only a very simple precedence network; it can be improved if forward and backward passes are included. This will also show the floats for each activity not on the critical path. Only be including more information will I find the shortest time needed to complete the project and maximum times of non-critical activities.